The odds were stacked against us being a shorter month and battling the copious amounts of rain we experienced this February, the construction team faced an up-hill battle. It pleases us to say that the boys still hit all their milestones, a great effort by the team all round!
Tony and his boys on the north side of the bridge at Neutral Bay began their rough-ins of the services and got on with deck work to prepare for the upcoming pour.
Over in St Ives it was the same narrative with the team carrying on with deck work as well as erecting the walls and forming hobs on the first floor.
The finishing trades were wrapping up with the internal works and started construction of the planter boxes.
All considered, it was an excellent result for each team and all the staff involved!