January Wrap-Up

 Just like that the new year was here! 2022 was upon us after the conclusion of the summer break and the team was raring to go.

We pick up where we left off in Bankstown with the crew carrying out the internal works, painting and finishing of the units. Landscaping works were also being conducted externally.

Up at Neutral Bay, Tony and the team had started the rough in on the ground floor and had a concrete pour of the ground floor slab, hitting another milestone early in the year.  

The boys over in St Ives poured their ground floor slab and continued on with the structural works on site. 

Having started closer to the middle of the month, we still didn’t miss a beat, hitting all the milestones for each job in their appropriate program.