October saw Dilcara recommence works at 100% after the Covid hinderances imposed upon us in the previous months. This milestone brought with it a positive aura for the company.
Bankstown was able to recommence works and get the entire site team and subcontractors on site. The team picked up right where they left off, producing the same, excellent standard of work and on time with the programme. The major milestone last month was the dismantling of the crane, we’re really on the home stretch now.
Our Neutral Bay team completed the bulk excavation, including the lift pit and the walls. The major milestone here was the erection of our hammerhead crane on the site. Allowing the boys to get a move on with the heavy lifting.
Still up on Sydney’s North, the St Ives team were powering through. The demolition was now complete and the excavation stage was well underway. The bulk and detailed excavation was finished along with the capping and piling.